1. Performing Site Tests:
-
Press the <Site Detail> key to
begin measurements.
-
Verify
Service Type is correct and
the Site Description is entered. {Use <SETUP> key to change
settings.}
-
Connect voltage clips and current plugs
(white side up). Normal definitions are: Red=”A”, Black=”B”, Yellow=”C”.
-
The Site Test data screen is displayed
(shown below). Review results for proper wiring.
Press to display
Vector Diagram. (Press again to see Waveform.)
|
|
2. Performing Meter
Tests:
-
Press the <System Power> key.
-
Verify
Service Type is correct and
the Site Description is entered. {Use <SETUP> key to change settings.}
-
Connect voltage clips and current plugs
(white side up). Normal definitions are: Red=”A”, Black=”B”, Yellow=”C”.
-
Press <MORE> key to enter the
meter constant (Kh or Ke) and the desired number of revolutions (or Total
Test Time).
-
Use the <PULSE> key or install the
IR pickup and adjust until meter pulses are indicated.
-
Press the <ENTER> key to start the
Meter Test and accumulate desired number of pulses. Review the
displayed results. (Press <Clear> to restart a test; press <ENTER>
to stop.)
|
|
3. Performing CT Tests
Performing CT Burden Test Only
-
Press the
<CT Tests>
key.
-
Enter the Site Description. (Use <SETUP>
key to change settings.)
-
Insert the Burden Test Plug (normally “A”
current plug) into the test switch “A” current position.
-
Press
<1>
or
<4>
key to select a CT Burden Test. {Press <6> to move to next CT.}
-
Review the CT Burden test results. If warning appears, press <Clear> to repeat test.
-
Move the Burden Test Plug to the “B” or
“C” position of the test switch. Press the <ENTER> key, and repeat
Steps 4-5 to test the next CT.
Performing CT Burden + Ratio Test
-
Press the
<CT Tests>
key.
-
Enter the Site Description. (Use <SETUP>
key to change settings.)
-
Insert the Burden Test Plug (normally “A”
current plug) into the test switch “A” current position.
-
Wrap the Flex Probe around the primary
conductors of the CT for A Phase (polarity: arrow toward the source).
-
Press <2> or <5> key to
select a CT Burden + Ratio Test. {Press <6> to move to next CT.}
-
Review the CT Burden + Ratio test
results. If warning appears, press <Clear> to repeat
test.
- Move the Burden
Test Plug to the “B” or “C” position of the test switch and the Flex Probe
to the next CT. Press the <ENTER> key, and repeat Steps 4-6 to
test the next CT.
After any CT Test, press
to display graph of results. |
|
|
| |
 |
|
Powermetrix, A Division of TEC
10737 Lexington Drive
Knoxville, TN 37932-3294 |
|
Phone:(865) 966-5856
Fax: (865) 675-1241
E-Mail: main@powermetrix.com |
|
|
| |
|
This
Site and its contents Copyright © 2007 Powermate
and Powermite are Trademarks of Technology for
Energy Corporation (TEC) All rights reserved. |